The Burkina Faso operator produced 360,857 ounces in the first nine months of the year. Explosives supply at Kiaka remains a bottleneck, but improved deliveries helped the company keep its annual guidance unchanged.
West African Resources is maintaining its 2026 production guidance of 430,000 to 490,000 ounces of gold, following a record third-quarter output of 127,950 ounces from its Sanbrado and Kiaka operations in Burkina Faso. Production for the year had reached 360,857 ounces by the end of September, according to the company’s September-quarter update.
Kiaka produced 76,030 ounces in the quarter, up 13% from the previous quarter. Sanbrado produced 51,920 ounces, down 10%.
A bottleneck, but no guidance cut
Kiaka’s explosives manufacturing and storage facility is still awaiting approval from Burkina Faso’s government. West African Resources said supply improved during the quarter, following better performance from its existing supplier and the addition of a second supplier. That allowed the company to increase waste-stripping activity at Kiaka and its Toega open pit, although explosives remain an operational bottleneck.
Explosives are used to blast hard rock and open access to ore. When supply is constrained, a mine may have to adjust where and how quickly it works. The latest update suggests the company has found ways to keep production moving while it waits for approval to operate its own facility.
The fourth quarter will decide where WAF lands
The arithmetic supports the lower end of the target. With 360,857 ounces produced by September, WAF needs about 69,000 more ounces in the final quarter to reach 430,000. Reaching 490,000 would require about 129,000 ounces, slightly above its third-quarter record.
That puts the upper end of the range under greater pressure. Kiaka’s improved output and supply situation provide support, but continued access to explosives and performance at both mines will shape the year-end result.
The next test is whether the company can sustain production through December while the Kiaka facility permit remains unresolved.